Project presentation / Concept stage

November 17, 2026

5027 Capehart Street

San Diego, CA 92117 / Proposed ADU over existing garage

Prepared for the Hastings family. Design, construction and finish planning in one package.

Proposed ADU with side stair access and two full-size front windows · Concept rendering · Select image to enlarge

Construction

$160,000

Design, fees + management

$50,750

Owner contingency

$21,075

Total planning budget

$231,825

Preliminary planning budget · 10% ALZA management added to construction, design and engineering · City fee reserve excluded from management · 10% owner contingency

The scope

Start with what’s here.
Plan what comes next.

The working concept is one new ADU above the existing garage, creating a two-story structure overall. The layout and construction approach follow the site assessment.

01 / EXISTING CONDITIONS

Understand the garage.

Measure the footprint and document the foundation, walls, roof, utility locations and relationship to the main home.

02 / NEW LIVING SPACE

Design the upper level.

Develop the living area, kitchen, bathroom and sleeping layout around the verified footprint, daylight and privacy. Bedroom count and square footage remain open.

03 / CONNECTIONS

Make it work together.

Develop exterior stair access along the garage’s left side, coordinating the landing, ADU entry and utility routing after site verification.

Explore the preliminary construction scope

Structure: Evaluate the existing foundation and framing; define strengthening or replacement work, upper-floor framing and lateral support with the engineer.

Exterior: Coordinate roof work, weatherproofing, windows, exterior doors, cladding and access stairs with the architectural design.

Systems: Review plumbing and sewer routes, electrical capacity, heating, cooling and ventilation.

Interiors: Develop insulation, drywall, kitchen, bathroom, flooring, trim and fixture selections after the layout is confirmed.

The design direction

A calm, considered interior.

Warm wood, light surfaces and clean detailing establish a calm interior direction. Final Capehart selections will be developed with the plans.

The budget

From design to construction.

Project delivery, design and engineering, agency reserves and a separate owner contingency—each identified in one planning budget.

Construction estimate provided by Peace of Mind Construction · CSLB License #1098789.

Pricing is subject to change based on final engineering, approved blueprints, and city requirements.

Capehart preliminary project estimate in US dollars
ItemAmount
Construction allowancesLabor, materials and installation; ALZA management shown separately$160,000
Designer servicesPredesign, design development, construction documents and permit processing$12,000
Structural + energy consultantsEngineering and energy compliance documentation$10,500
ALZA development management10% added to the $182,500 construction, design and engineering subtotal$18,250
City of San Diego fee reserve$10,000
Base budget$210,750
Owner-held contingency10% of the $210,750 base budget, including management and the city fee reserve$21,075
Total planning budget$231,825

ALZA’s 10% development management fee is added on top of construction ($160,000), designer services ($12,000) and structural + energy consultants ($10,500), totaling $18,250. The $10,000 City of San Diego fee reserve is excluded from this calculation. The owner-held contingency is a separate reserve and carries no management fee while unspent.

Owner contingency is held separately for unforeseen conditions and approved changes. It is not an automatic contractor charge. Final scope, provider pricing and management terms remain subject to separate written agreements.

The path forward

From idea to a coordinated plan.

The next milestone is a measured site visit. A construction schedule will be developed after the design, review process and contractor scope are defined.

  1. 01 / Document

    Site visit.

    Collect garage measurements, photos and available property drawings. Confirm the owner's program and budget goals.

  2. 02 / Evaluate

    Feasibility.

    Review the existing structure, site constraints, access options and applicable requirements with the design team.

  3. 03 / Coordinate

    Plans + pricing.

    Develop the layout, engineering scope and finish direction, then refine the planning budget with project-specific bids.

  4. 04 / Deliver

    Prepare to build.

    Complete plan review, confirm approvals, finalize contractor scope and establish the construction schedule.

ALZA Development

Let’s plan the next step.

5027 Capehart Street · San Diego, CA 92117

Discuss the project

Project status

Preliminary project presentation based on the proposed ADU-over-garage concept. The $231,825 planning budget is preliminary. Site conditions, structural feasibility, area, layout, final pricing and timeline remain subject to confirmation. This presentation is not an approved plan set or construction proposal.

Design reference